West Lake Tahoe Regional Water Treatment Plant
Project Overview
The new West Lake Tahoe Regional Water Treatment Plant will provide a steady and reliable source of drinking water from Lake Tahoe. It will be the main water supply for the McKinney-Quail water system. It also will have the capacity to serve other communities along Lake Tahoe’s west shore. This project will create a more connected water system for both drinking water and fire protection.
The TCPUD Board invested more than $30 million in this project. This represents one of the biggest investments ever made to improve and protect the west shore’s water supply.
The project included:
- Construction of the treatment plant and removal of temporary treatment facilities.
- Installation of submersible pumps and replacement of water intake pipes in Lake Tahoe.
- Building a new pump station at the lake.
- Installing new waterlines from Lake Tahoe to the treatment plant and replacement of existing lines.
We look forward to celebrating the grand opening with the community in 2025!
- Project Status
TCPUD is nearing completion of the new drinking water treatment plant in Tahoma, California, on the west shore of Lake Tahoe. The project replaces an existing temporary and seasonal water treatment facility currently located in Chambers Landing.
This TCPUD landmark project started in 2013 and has achieved the following major milestones:
- January 2013: Begin Preliminary Project Design
- October 2015: Complete California Environmental Quality Act (CEQA) Review
- June 2016: Acquire the Property for the Treatment Plant Building Site
- October 2016: Begin Final Project Design
- July 2018: TCPUD Board Authorization for Project Financing
- July 2019: Award Treatment Equipment Procurement Contracts
- December 2020: Advertise Project for Public Bidding
- May 2021: Award Construction Contract
- July 2021: Begin Construction
- October 2024: Submersible pumps installed, began testing and commissioning of the treatment plant
- Project Communications
- Project Documents
Potential Service Area of Treatment Plant
WLTRWTP Potential Service Area (PDF - 0.6MB)
Bid Summary - February 2021
WLTRWTP Pre-Bid Presentation (PDF - 12MB)
CEQA Documents
- Notice of Determination (NOD) – Filed Copies (PDF - 1.7MB)
- Mitigated Negative Declaration (PDF - 50kb)
- Adopted Resolution No. 15-29, Adopting a Mitigated Negative Declaration(MND) and Mitigation Monitoring & Reporting Program (MMRP) and Approving the Project (PDF - 0.4MB)
- Final Initial Study for the West Lake Tahoe Regional Water Treatment Plant (PDF - 17MB)
- Mitigation Monitoring & Reporting Program (MMRP) (PDF - 70kb)
- Learning Resources
Video Credit: Kennedy Jenks
Contact Us
For questions regarding the project, contact the TCPUD Engineering Manager, Sarah Hussong Johnson, at 530.580.6338 or email.
Funding Partners
California Department of Water Resources
California State Water Resources Control Board
United States Environmental Protection Agency
Placer County Water Agency